Cape Timber
Bellville, Western Cape
Project Scope
Phase 1: 741.65 kWp Rooftop PV
Phase 2: 135 kWp Carport PV 375kW/771kWh Energy Storage (Start Date 01/04/2026)
- PROJECT AGENT : Solasynergi
- Owners Engineer : Willem van Heerden
- Start Date : March 2021
- Completion Date : June 2021
- Duration : 3 Months
- Budget : R8.3 Million
Project Description
Grid Tied Roof Top 741.65kW PV