Project Scope
66kWp Ground Mount PV 250KW / 243 KWh Energy Storage
- PROJECT AGENT : SoSimple Energy
- Owners Engineer : Willem van Heerden
- Start Date : May 2024
- Completion Date : August 2024
- Duration : 3 Months
- Budget : R3 Million
Uninterrupted operations system for Cultura Fresh hydroponic farm.
Project Description
Design, Engineering and installing 66 kW ground mount solar with 250 kW / 243 KWh a containerised Battery Energy Storage System.